Our company (Tiba London for General Contracting) has started the second phase of the project to construct the industrial and storage workshops for the Abbasid Holy Shrine. The project consists of five workshops of 6,000 m² each in addition to two warehouses, on a total site area of 157,000 m². Work is currently underway on the five workshops, which are at the foundation stage, with approximately 2,500 m³ of concrete used in the foundations.

Infrastructure works include sewers, electrical installations and roads, as well as complementary and service buildings — an administration building, worker accommodation and football pitches. The project is expected to be completed within two years.